The Greater Chennai Corporation (GCC) has relaxed conditions for its 2026-27 road relaying contracts and will generate road work orders through the Tamil Nadu government's e-procurement portal hosted by the National Informatics Centre, according to a GCC official. The changes are aimed at widening contractor participation and curbing cartelisation of bidders.
Under the new procedure, work orders will be generated online once financial bids are opened, negotiations are completed and letters of acceptance are issued, so contractors will no longer need to approach officials separately to obtain the document required to begin execution. The GCC has also revised the rules for additional security deposits: only the lowest bidder must furnish the deposit, within two days of the first negotiation, through NEFT, RTGS or an electronic bank guarantee. Previously the requirement applied at the tender-opening stage, and the change is intended to protect the confidentiality of financial bids, the official said.
Bidders may now use owned or registered leased centralised hot mix plants, provided they hold a valid consent to operate certificate from the Tamil Nadu Pollution Control Board and the plant is located within 40 km of the GCC boundary. Bidders can participate in more than one package if they meet the eligibility conditions. The proposed works cover 753 roads across all 15 zones, including 66 bus route roads, spanning 167.55 km in total, of which 43.86 km comprises bus route roads. The estimated cost is ₹149.12 crore, including ₹68.31 crore for bus route road works. Tenders have been scheduled for November 27, December 3 and 7, 2026, according to the project details.
The GCC will retain 2.5% of the contract amount during the three-year defect liability period as a safeguard against defects, the official said. The amount will be withheld for three years, during which contractors must rectify defects, and they can replace it with an e-bank guarantee after completing the work. The provision is meant to protect the GCC against contractors quoting steep discounts and failing to complete works, the official said, noting that the Corporation had recently been receiving bids quoting discounts of as much as 20% to 30% below the estimated cost. The GCC rejected a request to relax the pollution consent requirement, citing National Green Tribunal directions, but permitted the use of registered leased plants subject to the prescribed conditions.